Hello everyone! Here is this week's free PMP exam sample question from the PM Exam Simulator.
Which process group consists of processes required to complete the work defined in the Project Management Plan?
A. Planning process group
B. Initiating process group
C. Monitoring and controlling process group
D. Executing process group
HINT: This process group involves coordinating people and resources, and managing stakeholder expectations.
All our questions are updated to the latest PMBOK® Guide standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a PMI Registered Education Provider.
Answer and Explanation:
The correct answer is D.
The Executing process group consists of processes required to complete the work defined in the Project Management Plan. This process group involves coordinating people and resources, and managing stakeholder expectations.