Hello everyone! Here is this week's free PMP exam sample question from the PM Exam Simulator.

Which is a work breakdown structure (WBS)?

A. It is a deliverable-oriented hierarchical decomposition of the work to be executed by the project team, to accomplish the project objectives and create the required deliverables.
B. It is a hierarchically organized depiction of the project organization arranged so that the work packages can be related to the performing organizational unit.
C. It is a hierarchically organized depiction of the resources by type to be used in the project.
D. It is a hierarchical tabulation of the physical assemblies, subassemblies and components needed to fabricate a manufactured product.

HINT: The WBS is a component of the Project Scope Baseline.

All our questions are updated to the latest PMBOK® Guide standard. Stop by at www.pm-prepcast.com/freesimulator and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at www.free-pm-exam-questions.com. We are a PMI Registered Education Provider.

Answer and Explanation:
The correct answer is A.

The WBS is a hierarchical decomposition of the total scope of the work to be carried out by the project team.