Hello everyone! Here is this week's free PMP exam sample question from the PM Exam Simulator.
Which of the following is a tool & technique of the Develop Project Charter process?
A. Project selection methods
B. Facilitation techniques
C. Project management methodology
D. Project management information system
HINT: The other tool and technique is Expert Judgment.
All our questions are updated to the latest PMBOK® Guide standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
We are a PMI Registered Education Provider.
Answer and Explanation:
The correct answer is B.
Expert Judgment and Facilitation Skills are two tools and techniques of the Develop Project Charter process.