Which of the following resource optimization techniques is used to adjust the activities of a project in order to keep resources within predefined limits?
A. Resource Leveling
B. Crashing
C. Fast Tracking
D. Resource Smoothing
HINT: This technique will not change the critical path.
All our questions are updated to the latest PMBOK® Guide standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a PMI Registered Education Provider.
Answer and Explanation:
The correct answer is D.
Resource Smoothing is used to adjust the activities of a schedule so that the resource requirements do not exceed certain resource limits.