Hello everyone! Here is this week's free PMP exam sample question from the PM Exam Simulator.
Which of the following statements about Project Scope and Product Scope is correct?
A. Project Scope is measured against the Project Management Plan
B. Product Scope is measured against the Project Management Plan
C. Project Scope is measured against the Product Requirements
D. Product Scope is measured against the Project Scope Statement
HINT: Project Scope defines the work that needs to be accomplished to deliver a product, whereas Product Scope is features and functions that characterize a product.
All our questions are updated to the latest PMBOK® Guide standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a PMI Registered Education Provider.
Answer and Explanation:
The correct answer is A.
According to the PMBOK Guide: "Completion of the project scope is measured against the Project Management Plan. Completion of the product scope is measured against the product requirements."