Hello everyone! Here is this week's free PMP exam sample question from the PM Exam Simulator.
You have just been assigned as the project manager for a new construction project. The Project Charter has been handed to you by your sponsor. You have performed the Stakeholder Analysis process and documented the information in the Stakeholder Register. Which of the following processes should be performed next?
A. Develop Project Management Plan
B. Define Activities
C. Determine Budget
D. Create WBS
HINT: Follow the recommended sequence from the PMBOK Guide.
All our questions are updated to the latest PMBOK® Guide standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a PMI Registered Education Provider.
Answer and Explanation:
The correct answer is A.
According to the scenario, you have just completed the project initiation phase, and in particular you have completed the Identify Stakeholders process. You should now perform the Develop Project Management Plan process, which comes after Identify Stakeholders.