fbpx
NEVER post copyrighted questions. Always state where questions come from. We take copyright violations very serious. Any copyrighted materials will be removed and the posters account will be deactivated.

TOPIC: Free PMP Exam Sample Question of the Week

Free PMP Exam Sample Question of the Week 7 years 10 months ago #7629

  • Mary Kathrine Padua
  • Mary Kathrine Padua's Avatar Topic Author
  • Offline
  • Administrator
  • Administrator
  • Posts: 353
  • Karma: 15
  • Thank you received: 122


Hello everyone! Here is this week's free PMP exam sample question from the PM Exam Simulator.

The PMBOK Guide recommends the use of the two different Three Point Estimating techniques for estimating project activity durations. The first is the PERT or Beta Distribution technique. What is the name of the other technique?

A. Alpha Distribution
B. Triangular Distribution
C. Normal Distribution
D. Gamma Distribution

HINT: Beta Distribution and Triangular Distribution are two Three-Point Distribution techniques.

All our questions are updated to the latest PMBOK® Guide standard. Stop by at www.pm-prepcast.com/freesimulator and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at www.free-pm-exam-questions.com . We are a PMI Registered Education Provider.

Answer and Explanation:
The correct answer is B.

Beta Distribution and Triangular Distribution are the two different Three Point Estimating techniques used for estimating project activity durations. Beta Distribution is the traditional PERT technique.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinJean KwandaAlexander AnikinElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login