Hello everyone! Here is this week's free PMP exam sample question from the PM Exam Simulator.

You are using Microsoft Project as a tool to manage the project. All the activities have been recorded and the Work Breakdown Structure has been prepared. Your project team wants to use different units of work for different resources. Which document establishes the information regarding units of measurement for resources on a project?

A. Enterprise Environmental Factors
B. Cost Management Plan
C. Project Charter
D. Performance Measurement Documents

HINT: Units of measurement are contained in one of the Project Management Plan's subsidiary plans.

All our questions are updated to the latest PMBOK® Guide standard. Stop by at www.pm-prepcast.com/freesimulator and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at www.free-pm-exam-questions.com . We are a PMI Registered Education Provider.

Answer and Explanation:
The correct answer is B.

The Cost Management Plan establishes units of measurement such as staff hours, staff days, and staff weeks.