Welcome, Guest
NEVER post copyrighted questions. Always state where questions come from. We take copyright violations very serious. Any copyrighted materials will be removed and the posters account will be deactivated.

TOPIC: Free PMP Exam Sample Question of the Week

Free PMP Exam Sample Question of the Week 7 months 17 hours ago #7374

  • Mary Kathrine Padua
  • Mary Kathrine Padua's Avatar
  • Offline
  • Administrator
  • Posts: 85
  • Thank you received: 44
  • Karma: 3


Hello everyone! Here is this week's free PMP exam sample question from the PM Exam Simulator.

You are performing Earned Value Management on your project. The Cost Baseline in Earned Value Management is also a part of:

A. Cost Estimating Baseline
B. Performance Baseline
C. Cost Measurement Baseline
D. Budget Baseline

HINT: The keyword to look here is 'performance'.

All our questions are updated to the latest PMBOK® Guide standard. Stop by at www.pm-prepcast.com/freesimulator and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at www.free-pm-exam-questions.com. We are a PMI Registered Education Provider.

Answer and Explanation:
The correct answer is B.

A Cost Baseline is a part of the Performance Baseline. The Performance Baseline is an approved plan for the project work to which the project execution is compared, and deviations are measured for management control. The Performance Baseline typically integrates the scope, schedule and cost parameters of a project.
Moderators: Yolanda Mabutas, Ahmed Amin, Scott Gillard, Fernando Jr Sinlao Lim, Mary Kathrine Padua, Chris Preziotti, Lazard Toe, ITBMC, MPM, CIPM, PMP, ITIL, Christian Winter, Kevin Nason, Mark Wuenscher, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®