Hello everyone! Here is this week's free PMP exam sample question from the PM Exam Simulator.
Your pharmaceutical drug manufacturing project is running late and you have deadlines to meet on your project. You want to replace some of the inefficient human resources with more talented human resources to finish the project on time. What risk response strategy is being followed in this context?
A. Share
B. Accept
C. Transfer
D. Mitigate
HINT: You are trying to reduce the likelihood of the risk occurrence.
All our questions are updated to the latest PMBOK® Guide standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a PMI Registered Education Provider.
Answer and Explanation:
The correct answer is D.
This is an example of risk mitigation. By replacing the human resources you are reducing the probability of the risk.