Free PMP Exam Sample Question of the Week 8 years 5 months ago #6331

  • Mary Kathrine Padua
  • Mary Kathrine Padua's Avatar Topic Author
  • Offline
  • Administrator
  • Administrator
  • Posts: 349
  • Karma: 15
  • Thank you received: 122


Hello everyone! Here is this week's free PMP exam sample question from the PM Exam Simulator.

An element of a Work Breakdown Structure that can be viewed at the lowest level of each branch is referred to as which of the following?

A. Control Account
B. Work Breakdown Structure Component
C. Work Package
D. Task

HINT: A work package is at the lowest level of a WBS.

All our questions are updated to the latest PMBOK® Guide standard. Stop by at www.pm-prepcast.com/freesimulator and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at www.free-pm-exam-questions.com . We are a PMI Registered Education Provider.

Answer and Explanation:
The correct answer is C.

A control account is a management control point where scope, budget, resources, actual cost and schedule are integrated and compared to earned value for performance measurement. Control accounts are placed at selected management points (specific components at selected levels) of the Work Breakdown Structure. A work package is a deliverable or project work component at the lowest level of each branch of the Work Breakdown Structure. Tasks are the results of further decomposition of work packages.
The following user(s) said Thank You: Jideofor Ebeogu
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinJean KwandaElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login