Hello everyone! Here is this week's free PMP exam sample question from the PM Exam Simulator.
Estimating costs demands expert skills. Which of the following is most important to document when estimating costs?
A. Documentation of all assumptions made
B. Documentation of any known constraints
C. Indication of the range of possible estimate
D. Documentation of the basis of the estimate
HINT: All of the choices are examples of the supporting details you must attach to each cost estimate. But which one is the most important?
All our questions are updated to the latest PMBOK® Guide standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a PMI Registered Education Provider.
Answer and Explanation:
The correct answer is D.
All of the choices are examples of the supporting details you must attach to each cost estimate. However, the documentation of the basis of the estimate is most important since this will be the justification for and reasoning behind the estimate you are presenting to your management for approval. All other information is secondary.