Hello everyone! Here is this week's free PMP exam sample question from the PM Exam Simulator.
You are managing a software development project. You want to create the basis that will be used later on for estimating, scheduling, executing, monitoring, and controlling the project work. Which process performs this activity?
A. Create WBS
B. Define Scope
C. Define Activities
D. Create Project Management Plan
HINT: Estimating is performed when the activities are defined and the schedule is prepared.
All our questions are updated to the latest PMBOK® Guide standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a PMI Registered Education Provider.
Answer and Explanation:
The correct answer is C.
Activities form a basis for estimating, scheduling, executing, and monitoring and controlling the project work. This is performed in the Define Activities process.