Our Website got Attacked Today!

At about 13:00 UTC today all our web-servers crashed due to a Distributed Denial of Service (DDOS) attack on the website. This attack (by an unknown group of hackers) caused the maximum allowed users to spike beyond what the system could handle. All three servers crashed and the message "Service Unavailable" was displayed.

We contacted our hosting company via phone right away and worked with them to restore the service. Now it was determined that it wasn't just the webservers that went down but unfortunately, the crash snowballed and took down the database servers as well.

Website service was restored again around 16:15 UTC.

We apologize for any inconvenience this attack may have caused you.

NEVER post copyrighted questions. Always state where questions come from. We take copyright violations very serious. Any copyrighted materials will be removed and the posters account will be deactivated.
  • Page:
  • 1

TOPIC: Question Free PMP Exam Sample Question of the Week

Free PMP Exam Sample Question of the Week 2 years 7 months ago #5817

  • Mary Kathrine Padua
  • Mary Kathrine Padua's Avatar Topic Author
  • Offline
  • Administrator
  • Administrator
  • Posts: 150
  • Karma: 5
  • Thank you received: 64
In a project, several risk response strategies may be used to effectively manage project risks. The strategy or mix of strategies should be determined when planning for risk responses. Which of the following statements best describes an Accept risk response strategy for negative risks or threats?

A. Adopting less complex processes
B. Purchasing insurance
C. Establishing Contingency Reserves
D. Extending the schedule

HINT: A risk acceptance strategy is adopted when it is impossible to eliminate all threats from a project. One of the answer choices is performed in the early stages of planning.

All our questions are updated to the latest PMBOK® Guide standard. Stop by at free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at www.free-pm-exam-questions.com . We are a PMI Registered Education Provider.

Answer and Explanation:
The correct answer is C.

The most common risk acceptance strategy is to establish contingency reserves, which is normally performed in the planning phase of a project.
The following user(s) said Thank You: Jideofor Ebeogu
  • Page:
  • 1
Moderators: Yolanda MabutasScott GillardMary Kathrine PaduaERIC BARTLETTKevin NasonMark Wuenscher, PMPTracy Shagnea, PMPJada GarrettGenevieve Pluviose, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login
Boost Your PMP Exam Prep in Only Six Hours! Join the FINAL Live PMP Coaching Class on March 10/11 for just $119. Learn More...
The PMP Exam is Changing in 2018
Simona and Cornelius
Free Interview - Listen Now

This interview with Simona Fallavollita (LinkedIn Profile) was recorded at the magnificient Project Management Institute (PMI)® Global Conference 2017 in Chicago, Illinois. We discuss the how, what, why and when of the changes that are coming to the PMP exam.

Thank you!
Cornelius Fichtner, PMP, CSM