fbpx
NEVER post copyrighted questions. Always state where questions come from. We take copyright violations very serious. Any copyrighted materials will be removed and the posters account will be deactivated.

TOPIC: IRR and Opportunity Cost

IRR and Opportunity Cost 9 years 1 month ago #5275

  • Mary
  • Mary's Avatar Topic Author
  • Visitor
  • Visitor
Which project would you select: A with IRR of 17% or B with opportunity cost of US $700000.

Ans 1) Project B
Ans 2) Project A
Ans 3) Either A or B
Ans 4) Cannot be determined

What would be the correct answer?

IRR and Opportunity Cost 9 years 1 month ago #5277

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Away
  • Administrator
  • Administrator
  • President, OSP International LLC
  • Posts: 1982
  • Karma: 119
  • Thank you received: 606
Hello Mary,

Please provide the source (book, website, etc.) where you found this question. We want to give credit where credit is due.

Thank you!
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC

IRR and Opportunity Cost Ans -4 9 years 1 month ago #5296

  • RAVI
  • RAVI's Avatar Topic Author
  • Visitor
  • Visitor

Mary wrote: Which project would you select: A with IRR of 17% or B with opportunity cost of US $700000.

Ans 1) Project B
Ans 2) Project A
Ans 3) Either A or B
Ans 4) Cannot be determined

What would be the correct answer?

IRR and Opportunity Cost 9 years 1 month ago #5302

  • Steve Sandoval
  • Steve Sandoval's Avatar
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 49
  • Thank you received: 11
Mary,

Typically for a comparison to be useful, you need to compare like to like. In this case, you've got a bit of an "apples vs. oranges" situation -- you have the IRR for one item, and the opportunity cost for the other item. You really can't say unless you know the same metric for both things that you're comparing.
Steve Sandoval, PMP
Community Moderator

IRR and Opportunity Cost 9 years 1 month ago #5313

  • Anil
  • Anil's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 7
  • Thank you received: 0
As an extension to this question, can you select a project only with the given opportunity cost ? Ex.

Project A = $1 mil (Should the project with the least opportunity cost (lost) be the best choice ?)
Project B = $2 mil
Project C = $3 mil
Project D = $4 mil

Thanks.
Last edit: by Anil.

IRR and Opportunity Cost 9 years 1 month ago #5315

  • Ahmed Amin
  • Ahmed Amin's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 300
  • Karma: 10
  • Thank you received: 73
Hello Anil,

There are many techniques used in project selection. one of which is the opportunity cost "This is the cost that we are giving up by choosing some other project". if we have multiple projects to choose from, we will choose the one with lesser opportunity cost.

It is worth mentioning that opportunity cost involves many factors other than just the projects price.
Ahmed Amin Abdullah, PMP
Community Moderator
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinJean KwandaElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login