fbpx

Reply: Free PMP Exam Sample Question of the Week!

Name
E-mail
Your e-mail address will never be displayed on the site.
Subject
Message

Topic History of : Free PMP Exam Sample Question of the Week!

Max. showing the last 6 posts - (Last post first)
9 years 2 weeks ago #5269

's Avatar



Question:

Your team finished creating the initial version of the Risk Register during your latest workshop. What is the next thing that you should do?

A. Define the probability of occurrence and the impact for each risk
B. Identify the risk effects and assign a numerical rating to each
C. Review cost planning to ensure that enough risk reserve is available
D. Identify, analyze and plan for newly-arisen risks


Hint: You've completed your risk identification.


All our questions are updated to the latest PMBOK® Guide standard. Stop by at free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at www.free-pm-exam-questions.com . We are a PMI Registered Education Provider.

Answer and Explanation:

The Correct Answer is A.

The scenario says that you have finished creating the initial version of the Risk Register. Finished means that you have completed identifying risks and prepared the risk register.
Your next step is therefore to move into the Perform Qualitative Risk Analysis process, which is the process where (among other things) you will prioritize risks for further analysis by assessing and combining the probability of occurrence and impact.

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login