Question:

You are managing a telecommunications network deployment project. You are employed by a telecom equipment company that specializes in installing and implementing the telecom equipment for this project. Since your company is not experienced in civil works, you have outsourced all of the civil works activities to an outside contractor. You are now finalizing all of the open claims with this contractor. Which project management process are you currently performing?

A. Close Procurements
B. Close Project or Phase
C. Control Procurements
D. Validate Scope


Hint: Which project management process involves administrative activities such as finalizing open claims, updating records to reflect final results, and archiving such information for future use?


All our questions are updated to the latest PMBOK® Guide standard. Stop by at free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at www.free-pm-exam-questions.com . We are a PMI Registered Education Provider.

Answer and Explanation:

The Correct Answer is A.

The Close Procurements process also involves administrative activities such as finalizing open claims, updating records to reflect final results, and archiving such information for future use. Close Procurements addresses each contract applicable to the project or a project phase.
Moderators: Yolanda MabutasAnne BMary Kathrine PaduaJohn Paul BugarinJean KwandaElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login