NEVER post copyrighted questions. Always state where questions come from. We take copyright violations very serious. Any copyrighted materials will be removed and the posters account will be deactivated.
  • Page:
  • 1

TOPIC: Free PMP Exam Sample Question of the Week

Free PMP Exam Sample Question of the Week 2 years 8 months ago #4664

  • Anne B
  • Anne B's Avatar Topic Author
  • Visitor
  • Visitor


Question:

Which of the following techniques can help in controlling project risks?

A. Quality Audit
B. Pareto Diagram
C. How-How Diagram
D. Reserve Analysis


Hint: Consider the tools and techniques for the Control Risks process.


All our questions are updated to the latest PMBOK® Guide standard. Stop by at free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at www.free-pm-exam-questions.com . We are a PMI Registered Education Provider.

Answer and Explanation:

The Correct Answer is D.

Reserve analysis, risk audits and status meetings are all tools and techniques of the Control Risks process.
  • Page:
  • 1
Moderators: Yolanda MabutasAnne BAhmed AminScott GillardMary Kathrine PaduaERIC BARTLETTKevin NasonMark Wuenscher, PMPTracy Shagnea, PMPJada Garrett

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®