fbpx
NEVER post copyrighted questions. Always state where questions come from. We take copyright violations very serious. Any copyrighted materials will be removed and the posters account will be deactivated.

TOPIC: Free PMP Exam Sample Question of the Week

Free PMP Exam Sample Question of the Week 9 years 6 months ago #4664

  • Anne B
  • Anne B's Avatar Topic Author
  • Visitor
  • Visitor


Question:

Which of the following techniques can help in controlling project risks?

A. Quality Audit
B. Pareto Diagram
C. How-How Diagram
D. Reserve Analysis


Hint: Consider the tools and techniques for the Control Risks process.


All our questions are updated to the latest PMBOK® Guide standard. Stop by at free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at www.free-pm-exam-questions.com . We are a PMI Registered Education Provider.

Answer and Explanation:

The Correct Answer is D.

Reserve analysis, risk audits and status meetings are all tools and techniques of the Control Risks process.
Moderators: Yolanda MabutasAnne BMary Kathrine PaduaJohn Paul BugarinJean KwandaElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login