Free PMP Exam Sample Question of the Week 2 years 1 week ago #4664

  • Anne B
  • Anne B's Avatar


Which of the following techniques can help in controlling project risks?

A. Quality Audit
B. Pareto Diagram
C. How-How Diagram
D. Reserve Analysis

Hint: Consider the tools and techniques for the Control Risks process.

All our questions are updated to the latest PMBOK® Guide standard. Stop by at free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at www.free-pm-exam-questions.com. We are a PMI Registered Education Provider.

Answer and Explanation:

The Correct Answer is D.

Reserve analysis, risk audits and status meetings are all tools and techniques of the Control Risks process.