fbpx

Reply: Free PMP Exam Sample Question of the Week

Name
E-mail
Your e-mail address will never be displayed on the site.
Subject
Message

Topic History of : Free PMP Exam Sample Question of the Week

Max. showing the last 6 posts - (Last post first)
9 years 7 months ago #4560

Anne B

Anne B's Avatar



Question:

Which of the following performance metrics measures project performance against the project scope?

A. Schedule Performance Index
B. Cost Performance Index
C. Cost Variance
D. No metric is used


Hint: SPI is Schedule Performance Index, CPI is Cost Performance Index.



All our questions are updated to the latest PMBOK® Guide standard. Stop by at free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at www.free-pm-exam-questions.com . We are a PMI Registered Education Provider.

Answer and Explanation:

The Correct Answer is D.

SPI is Schedule Performance Index, CPI is Cost Performance Index. None of these metrics measure the project performance against the project scope.
In fact, there is no metric mentioned whatsoever in the PMBOK Guide that measures this kind of performance. The performance can be measured against the scope baseline but there is no metric for doing so. The question is trying to trick you.

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login