fbpx
NEVER post copyrighted questions. Always state where questions come from. We take copyright violations very serious. Any copyrighted materials will be removed and the posters account will be deactivated.

TOPIC: Free PMP® Exam Sample Question

Free PMP® Exam Sample Question 1 month 1 week ago #31647

  • Mary Kathrine Padua
  • Mary Kathrine Padua's Avatar Topic Author
  • Offline
  • Administrator
  • Administrator
  • Posts: 385
  • Karma: 16
  • Thank you received: 128


An organization has a policy that a change control board (CCB) must review all change requests for every project in the organization, and that the CCB follows the recommended activities outlined in the PMBOK® Guide. Project managers and project team members are not allowed to be part of the CCB.

Based on this scenario, which of the following activities might be performed by members of the CCB?

A. Submitting a change request
B. Implementing approved change requests
C. Initiating and closing a project
D. Monitoring implementation of approved changes

HINT: Which option includes the responsibilities of the project manager and the project team?

All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days. We are a trusted and experienced education provider.

Answer and Explanation:
The correct answer is A.

The change control board (CCB) is a formally chartered group responsible for reviewing, evaluating, approving, deferring, or rejecting change requests. The CCB can include project stakeholders, and a change may be requested by any stakeholder involved with the project.

Therefore, it is possible for a member of the CCB to submit a change request.

Details for each option:

A. Correct. The CCB can include project stakeholders, and a change may be requested by any stakeholder involved with the project. Therefore, it is possible for a member of the CCB to submit a change request.

B. Incorrect. Implementing approved change requests occurs during the Direct and Manage Project Work process, which is the responsibility of the project manager and the project team rather than the CCB.

C. Incorrect. A project can be initiated by the project sponsor. However, closing the project is typically the responsibility of the project manager. According to the scenario, the project manager is not a member of the CCB. Therefore, even if the project sponsor is a member of the CCB and can initiate the project, this answer choice can be eliminated as at least one of its parts does not hold true.

D. Incorrect. Monitoring the implementation of approved change requests is part of the Monitor and Control Project work process. The CCB reviews change requests as part of the Perform Integrated Change Control process rather than the Monitor and Control Project Work process. Additionally, the responsibility to monitor the implementation of the approved change requests lies with the project manager, not CCB.

Reference: A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Seventh Edition, Project Management Institute Inc., 2021,
2.5.7 MONITORING NEW WORK AND CHANGES

Process Groups: A Practice Guide, Project Management Institute Inc., 2023,
7.2 Perform Integrated Change Control
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinJean KwandaAlexander AnikinElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login