fbpx
NEVER post copyrighted questions. Always state where questions come from. We take copyright violations very serious. Any copyrighted materials will be removed and the posters account will be deactivated.

TOPIC: Free PMP® Exam Sample Question

Free PMP® Exam Sample Question 4 months 1 week ago #31533

  • Mary Kathrine Padua
  • Mary Kathrine Padua's Avatar Topic Author
  • Offline
  • Administrator
  • Administrator
  • Posts: 391
  • Karma: 16
  • Thank you received: 129


The project aims to investigate the feasibility of constructing a hydroelectric dam from a technical, economic, and social point of view. The project charter created by the project manager on behalf of the project sponsor is now approved.

Which of the following processes should be performed next?

A. Develop Project Management Plan
B. Identify Risks
C. Identify Stakeholders
D. Develop Project Charter

HINT: All of the project initiation processes should be completed before moving on to the planning processes.

All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days. We are a trusted and experienced education provider.

Answer and Explanation:
The correct answer is C.

The Identify Stakeholders process is the process of identifying all people or organizations impacted by the project and documenting relevant information regarding their interests, involvement, and impact on project success.

Both the Develop Project Charter process and the Identify Stakeholders process are part of the Initiating Process Group which should be completed before proceeding to the processes in the Planning Process Group.

In this scenario, since the project charter has been developed and approved, the Identify Stakeholders process should be performed next.

Details for each option:

A. Incorrect. Although one may start to develop the project management plan before identifying all the stakeholders, it would be quite difficult to complete the project management plan without identifying and soliciting requirements from the stakeholders. Additionally, the stakeholder engagement plan is one of the subsidiary plans of the project management plan. For these reasons, it would be best to perform the Identify Stakeholders process before the Develop Project Management Plan process.

B. Incorrect. The stakeholder register, which is an output of the Identify Stakeholders process, is an input to the Identify Risks process. Therefore, the Identify Stakeholders process should be completed before the Identify Risks process.

C. Correct. The main output of the Identify Stakeholders process, the stakeholder register, is used as an input to many other project management processes, making it necessary to identify the stakeholders before performing other processes. Additionally, both the Identify Stakeholders process and the Develop Project Charter process are part of the Initiating Process Group, which should be completed before moving on to the Planning Process Group. Therefore, the Identify Stakeholders process should be performed right after the project charter has been developed and approved.

D. Incorrect. Based on the scenario, the project charter has already been developed so this answer choice can be eliminated.

Reference: A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Seventh Edition, Project Management Institute Inc., 2021:
3.3 EFFECTIVELY ENGAGE WITH STAKEHOLDERS
2.1.1.1 Identify

Process Groups: A Practice Guide, Project Management Institute Inc., 2023,
4.2 Identify Stakeholders
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinJean KwandaAlexander AnikinElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login