Confirm text replacement with template category text
All the text in the message will be deleted and replaced by text from category template.
3 years 1 month ago #26537 | |
---|---|
Arjie Maghanoy
|
The team has just reported to you that they have completed the Plan Quality Management process. You review their work and see that they have produced the quality management plan, and made the necessary updates to the project management plan and project documents. What did they forget? A. Determine quality metrics B. Define quality roles and responsibilities C. Revise the lessons learned register D. Update the requirements traceability matrix HINT: An output of the Plan Quality Management process which serves as an input to the Manage Quality and Control Quality processes is missing. All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days. We are a trusted and experienced education provider. Answer and Explanation The correct answer is A. The question suggests that the Plan Quality Management process was performed, and an element of this process was missed. Quality metrics are a project document that serves as one of the outputs of the Plan Quality Management process. This document was not mentioned in the scenario. All of the other outputs are stated as being completed. A quality metric, an input to the Manage Quality and Control Quality processes, specifically describes a project or product attribute and how these processes will verify compliance with it. Therefore, quality metrics are what was most likely missed by the project team. One may argue that quality metrics should be part of the quality management plan just like the quality roles and responsibilities. While this may sound counter-intuitive, the <em>PMBOK<sup>®</sup> Guide</em> describes quality metrics as a separate standalone document. The complete list of the components of the project management plan vs. project documents can be found on page 89, Table 4-1. Project Management Plan and Project Documents. Details for each option: A. Determine quality metrics Correct. A quality metric specifically describes a project or product attribute and how the Manage Quality and Control Quality processes will verify compliance with it. Quality metrics are an output of the Plan Quality Management process and were not stated as being completed. Therefore, the quality metrics are what were most likely missed by the project team. B. Define quality roles and responsibilities Incorrect. Determining quality roles and responsibilities is a key component of the quality management plan. The question indicates that the quality management plan has been developed. Therefore, this element was not missed by the project team. C. Revise the lessons learned register Incorrect. The lessons learned register is a project document that may be updated as part of the Plan Quality Management process. The question states that all project documents were updated (revised). D. Update the requirements traceability matrix Incorrect. The requirements traceability matrix is a project document that may be updated during the Plan Quality Management process. The scenario indicates that all project documents were updated. Therefore, this answer choice can be eliminated. Reference: A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) 287 |
OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®
Company Info
- Home
- PMP®
- PMI-ACP®
- CAPM®
- CIPP/E®
- PDUs
- AI
- Free
- Free PM PrepCast Training
- Free PM PrepCast Exam Simulator
- Free PMP® Practice Exam
- The Free PM PrepCast
- Free PMP® Exam Guides
- Free PMP® Exam Newsletter
- Free PMP® Webinars
- All Free PMP® Exam Resources...
- The Free Agile PrepCast
- Free PMI-ACP® Exam Newsletter
- All Free PMI-ACP® Exam Resources...
- Free CAPM® Exam Newsletter
- All Free PDU Resources...
- Corporate
- Articles
- PMP® Study Guide
- PMP® Certification Cost
- 35 Hours of Project Management Education
- Knowledge Areas & Process Groups
- How to Fill in the PMP Application
- PMP® Certification Exam
- How to get PMP Certification
- PMP® ITTO
- PMP® Exam Questions
- PMP® Certification Bangalore
- PMP® Formulas
- Failed PMP Exam
- PMI-ACP Certification Study Guide
- CAPM Certification Study Guide
- 12 Project Management Principles Explained by Experts
- Project Management Certifications Career Advancement
- PMP vs Certifications
- Project Management Organization Company Benefits
- Project Management Organizations Importance
- Reviews
- Forum