Here is our free PMI-ACP Exam sample question of the week.
Question 140: Which of the following best describes progressive elaboration?
A. It allows teams to pull new information into plans when it becomes available.
B. It engages stakeholders in project decisions.
C. It determines expectations.
D. It allows documentation of all stakeholder needs across the project.
Here is our free PMI-ACP Exam sample question of the week.
Question 139: Jasmine is writing down a goal she wants to meet. She starts with a very specific road map of what the result should be. She knows that she can get it done and has tracking mechanisms documented. Carol knows the goal is realistic as well. Which of the following is missing from her goal setting approach?
A. Specific
B. Measurable
C. Attainable
D. Time-based
In an Agile project, it is typical that the cost and time would be more rigid and the scope of work would be more flexible. The opposite is true in a Waterfall type of project
Here is our free PMI-ACP Exam sample question of the week.
Question 138: When you’re reviewing constraints on an Agile project, which of the following are considered not as flexible as others?
A. Scope and quality
B. Time and quality
C. Cost and scope
D. Cost and time