Correct Answer to Q#136: C

In this case, the must-haves versus the won’t-haves points to prioritization using the MoSCoW approach.
1 week 6 days ago #32347

Sameer Menda

Sameer Menda's Avatar

Here is our free PMI-ACP Exam sample question of the week.

Question 136: Your customer is working very closely with your team on prioritization of value for their product. There are certain items that must be in the final product no matter what and others that won’t be included unless different information is presented at a later date. Which of the following prioritization techniques does it look like they used?
A. Dot voting
B. Kano analysis
C. MoSCoW
D. Monopoly Money
1 week 6 days ago #32346

Sameer Menda

Sameer Menda's Avatar

Correct Answer to Q#135: D

A service level agreement allows for terms and conditions to be determined in the beginning so that future changes in scope won’t result in renegotiations throughout the project.
3 weeks 16 hours ago #32324

Sameer Menda

Sameer Menda's Avatar

Here is our free PMI-ACP Exam sample question of the week.

Question 135: You are being tasked by your organization to create a statement of work that will be utilized in the procurement process. The legal department explains to you that they want to make sure that all terms and conditions are negotiated and agreed to up front. Then, when scope needs to be changed, there is more flexibility in the process. To what type of agreement is the legal department referring?
A. Fixed-price contract
B. Cost-reimbursable contract
C. Time and materials contract
D. Master service level agreement
3 weeks 16 hours ago #32323

Sameer Menda

Sameer Menda's Avatar

Correct Answer to Q#134: B

Using a more flexible type of contract on Agile projects allows for updates or change in scope without any penalty or legal breach of contract.
3 weeks 6 days ago #32299

Sameer Menda

Sameer Menda's Avatar

Here is our free PMI-ACP Exam sample question of the week.

Question 134: Agile contracts differ from Waterfall projects in which of the following ways?
A. They are longer term to accommodate iterations.
B. They can use a fix and switch contract to allow for changes in scope.
C. They can be adapted at any time.
D. The can be updated for scope changes that have been approved through change control systems.

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login