Here is our free PMI-ACP Exam sample question of the week. This question is taken from The PM Exam Simulator at
www.pm-exam-simulator.com/pmi-acp
Question 76: An agile team used planning poker to estimate user stories. After all team members read a user story, the facilitator asks everyone to choose a card with an estimated number of ideal days to complete a user story and then reveal the card. If estimates were widely different, the facilitator would immediately ask for re-estimates until all the estimates converge. What did the facilitator do wrong?
A ) Participants used ideal days as the unit for the estimates.
B ) Participants re-estimated immediately after everyone revealed their cards.
C ) Cards were revealed when the process should have been anonymous.
D ) The facilitator did nothing wrong and played by the rules.