fbpx

Reply: Free CAPM® Exam Sample Question

Name
E-mail
Your e-mail address will never be displayed on the site.
Subject
Message

Topic History of : Free CAPM® Exam Sample Question

Max. showing the last 6 posts - (Last post first)
4 years 2 months ago #19586

Arjie Maghanoy

Arjie Maghanoy's Avatar



Which of the following is not included in the risk register?

A. Revised stakeholder tolerance
B. A list of identified risks
C. Prioritized list of quantified risks
D. Resolving issues or conflicts

HINT: Remember that the risk register is created in the Identify Risks process and will be updated in other risk management processes as the project progresses.

All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days.

Answer and Explanation:
The correct answer is A

The risk register is a primary output of the Identify Risks process, which includes a list of identified risks with potential responses to some of them if possible. The risk register will be updated with more detailed information about risk characteristics, risk priority as the result of risk analysis processes. While stakeholder's tolerances, which are defined based on the organization's risk appetite, are expected to be reviewed during the Plan Risk Management process and are a part of the risk management plan.


Details for each option:

A. Revised stakeholder tolerance
Correct. Stakeholder tolerance, when applied, is revised in the Plan Risk Management process and documented in the risk management plan, not in the risk register.

B. A list of identified risks
Incorrect. The list of identified risks is the main result of the Identify Risks process and documented in the risk register.

C. Prioritized list of quantified risks
Incorrect. The prioritized list of quantified risks could be updated in the risk register as a result of the Perform Quantitative Risk Analysis process.

D. Potential responses to identified risks
Incorrect. During identifying risks, potential responses to some identified risks may be documented in the risk register to provide the project team more information for further analysis.

Reference: Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) 405-408

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login