fbpx
NEVER post copyrighted questions. Always state where questions come from. We take copyright violations very serious. Any copyrighted materials will be removed and the posters account will be deactivated.

TOPIC: Free CAPM® Exam Sample Question

Free CAPM® Exam Sample Question 3 years 1 month ago #26650

  • Arjie Maghanoy
  • Arjie Maghanoy's Avatar Topic Author
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 182
  • Karma: 21
  • Thank you received: 66


Which of the following needs to be updated during the closing phase of a project?

A. WBS
B. Quality management plan
C. Benchmarks
D. Operational and support documents

HINT: Think which option is a valid output to the Close Project or Phase process.

All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days.

Answer and Explanation:
The correct answer is D.

The Close Project or Phase process has the following outputs:

1. Project document updates
2. Final product, service, or result transition
3. Final report
4. Organizational process assets updates

The organizational process assets that are updated as a result of the Close Project or Phase process include project documents, operational and support documents, project or phase closure documents, and lessons learned repository.

Details for each option:

A. WBS
Incorrect. The WBS is not an output of the Close Project or Phase process.

B. Quality management plan
Incorrect. The quality management plan is not an output of the Close Project or Phase process.

C. Benchmarks
Incorrect. Benchmarks are not an output of the Close Project or Phase process.

D. Operational and support documents
Correct. Operational and support documents are included within organizational process assets updates, which are output to the Close Project or Phase process.


Reference: A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) 128
Last edit: by John Paul Bugarin.
Moderators: John Paul Bugarin

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login