fbpx
NEVER post copyrighted questions. Always state where questions come from. We take copyright violations very serious. Any copyrighted materials will be removed and the posters account will be deactivated.

TOPIC: Free PMP® Exam Sample Question of the Week!

Free PMP® Exam Sample Question of the Week! 3 years 4 months ago #24725

  • Arjie Maghanoy
  • Arjie Maghanoy's Avatar Topic Author
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 182
  • Karma: 21
  • Thank you received: 66


Which document describes how to create the WBS?

A. Project scope statement
B. Requirements traceability matrix
C. Scope management plan
D. Requirements management plan

HINT: Notice that only the project management plan provides such guidelines.

All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days.

Answer and Explanation:
The correct answer is C.

The scope management plan specifies how to create the work breakdown structure (WBS) from the detailed project scope statement and how the WBS will be maintained and approved.

Details for each option:

A. Project scope statement
Incorrect. The project scope statement is the description of the project scope, major deliverables, assumptions, and constraints. It does not contain any process or guidelines.

B. Requirements traceability matrix
Incorrect. The requirements traceability matrix links product requirements from their origin to the deliverables that satisfy them.

C. Scope management plan
Correct. The scope management plan is a component of the project or program management plan that describes how the scope will be defined, developed, monitored, controlled, and verified.

D. Requirements management plan
Incorrect. The requirements management plan describes how requirements will be analyzed, documented, and managed. It focuses on requirement management and does not provide guidelines on how to create the work breakdown structure.

Reference: A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) 157
The following user(s) said Thank You: Anu Maletira
Last edit: by John Paul Bugarin.
Moderators: John Paul Bugarin

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login