TOPIC: PMI-ACP Question/Topic of the week : Season-8

PMI-ACP Question/Topic of the week : Season-8 2 months 4 days ago #32991

  • Sameer Menda
  • Sameer Menda's Avatar Topic Author
  • Offline
  • Moderator
  • Moderator
  • Posts: 367
  • Thank you received: 10
Here is our free PMI-ACP Exam sample question of the week.

Question 148: Chris identified a new risk early in the first iteration. This is due to the use of the newest technologies and not much is known about how to solve it. What is the best thing for Chris to suggest in order to manage the situation?
A. Document the risk in the risk-adjusted backlog, and wait for the product owner to review.
B. Perform a risk-based spike.
C. Update the backlog.
D. Move the risk affected work into the backlog for future iterations.
Sameer Menda | PMP, PMI-ACP, PSM II
Community Moderator

Follow: twitter.com/corneliusficht
Like: www.facebook.com/PrepCast/
Subscribe: www.project-management-podcast.com

PMI-ACP Question/Topic of the week : Season-8 1 month 4 weeks ago #33008

  • Sameer Menda
  • Sameer Menda's Avatar Topic Author
  • Offline
  • Moderator
  • Moderator
  • Posts: 367
  • Thank you received: 10
Correct Answer to Q#148: B

Chris should discuss performing a risk-based spike with the product owner and move forward with approval to determine if the risk can be mitigated.
Sameer Menda | PMP, PMI-ACP, PSM II
Community Moderator

Follow: twitter.com/corneliusficht
Like: www.facebook.com/PrepCast/
Subscribe: www.project-management-podcast.com

PMI-ACP Question/Topic of the week : Season-8 1 month 2 weeks ago #33030

  • Sameer Menda
  • Sameer Menda's Avatar Topic Author
  • Offline
  • Moderator
  • Moderator
  • Posts: 367
  • Thank you received: 10
Here is our free PMI-ACP Exam sample question of the week.

Question 149: Gita is in the process of restructuring existing computer code without changing its behavior. Peter asks her what she is working on. How will Gita answer that question?
A. I’m cleaning up tech debt.
B. I’m trying to build in lead time.
C. I’m refactoring the code.
D. I’m building software.
Sameer Menda | PMP, PMI-ACP, PSM II
Community Moderator

Follow: twitter.com/corneliusficht
Like: www.facebook.com/PrepCast/
Subscribe: www.project-management-podcast.com

PMI-ACP Question/Topic of the week : Season-8 1 month 1 day ago #33063

  • Sameer Menda
  • Sameer Menda's Avatar Topic Author
  • Offline
  • Moderator
  • Moderator
  • Posts: 367
  • Thank you received: 10
Correct Answer to Q#149: C

Gita is refactoring the code to make the code easier to read and edit as well as to clean it up without impacting the actual performance of the code.
Sameer Menda | PMP, PMI-ACP, PSM II
Community Moderator

Follow: twitter.com/corneliusficht
Like: www.facebook.com/PrepCast/
Subscribe: www.project-management-podcast.com
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinSameer MendaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login