Question 9: During a retrospective meeting after a failed sprint, emotions run high as the team members blame each other for the failure. Phrases like “He always forgets to check in his code!” or “You never listen to what I have to say!” predominate this heated debate. What is the first thing that an experienced agile coach should do in such situation?
A) Sit back for a while and observe the team members
B ) Intervene immediately to avoid further harm
C) Call in a human resources department representative
D) Start a coaching session with the team members